Boracay Dreaming

New front cabin storage and panels
Lots of strong westerlies
10/26/2009, Sydney Harbour

I have done the port and starboard paneling in the front cabin and installed a light.
Estimated Total Hours:- 3650

| | More
Porthole paneling
Two months of wet, windy weather...
07/29/2009, Sydney Harbour...

I've put in a photo of the #2 port porthole paneling. It's the only job actually finished in the last two months.
Flu, windy and wet weather (I'm now on a mooring) have all slowed me down.
I'm now working on the front cabin, which (hopefully) is the last of the big tricky interior furniture jobs.

Estimated Total Hours:- 3470

| | More
The complete head..
Wet and windy
05/20/2009, Sydney Harbour

I have finished doing the locker doors and the paneling for the head.
I used "A" bond C/D pine ply, primed with thinned generic epoxy and topcoated with 2-3 coats single pack white polyurethane enamel.

Estimated Total Hours:- 3270

| | More