Boracay Dreaming

Dodger "Finished"
Just had a very good weekend
10/20/2008, Sydney Harbour

Dodger is now finished. Glazing will come later.
Estimated hours for dodger :- 220
Estimated Total Hours :- 2590

| | More
Dodger, Davits and Gas Bottle Mounts
Hot and windy
09/28/2008, Sydney Harbour

Work proceeds slowly on the dodger, the davits and the gas bottle mounts.
Estimated Total Hours :- 2500

| | More
Installing the headliner
Cold, wet and windy
08/07/2008, Sydney Harbour

When it is too cold, wet or windy to work outside I continue with the inside. Current priority - the headliner in the main cabin.
Estimated Total Hours :- 2370

| | More